This page is an automatically maintained audit log for the weekly legal requirements monitoring task covering EG Utility's products (Xellent/AX7, Zynergy, SonWin, ProBill, Gasell, Bright). It complements the main Legal requirements - EG Utility list.
How this log works: each run adds one new dated entry below the most recent one. Entries are never edited or deleted, so the full history of what was found and what was changed remains visible here. Any change made to the main requirements table (new row added, status cell updated) is also tracked automatically by Confluence's own page version history on that page.
2026-08-17 – Log created
Monitoring log initialized. No scan has run yet; the first automated weekly run is scheduled for the next Monday.
2026-08-19 - Weekly scan
Queued for review (Pending Review page, 4 new items):
- Origin marking of electricity (Ursprungsmärkning av el) - new Ei regulation in force 2026-02-01, requires use of Swedish residual mix. Source: Ei 2025-12-12. Not previously tracked; likely affects Zynergy Trade/Invoice and/or Xellent invoicing.
- New Ei risk-management regulations for fixed-price/mix electricity contracts, in force 2026-05-01. Source: Ei 2026-03-27. Not previously tracked; likely affects Zynergy Trade contracts/pricing.
- REMIT II (Regulation (EU) 2024/1106), new wholesale energy reporting duties in force 2026-04-29. Source: Baker McKenzie / ACER. No existing REMIT reporting code found in a zynergy repo search; genuinely new scope for the trading module.
- Danish consumer protection & sanctions reform for retail electricity (Lovforslag L 53), in force 2026-01-01. Source: Folketinget / retsinformation.dk. Distinct from the existing "Regret button" row; likely affects SonWin.
Auto-updated in the main list (5 rows, routine maintenance of already-confirmed items):
- "Information regulation grid owner" - Comment and Source updated: Ei has now decided the regulation (2026-06-08), previously only a proposal.
- "Power tariffs" - Comment and Source updated: Ei tasked (2026-03-13) with developing a new power-tariff model and repealing existing regulations.
- "New Gas market requirement" - Confirmed date, Comment and Source updated: Ei decided two new gas revenue-framework regulations, applying from 2026-05-11.
- "Assigned supplier is replace by supplier of last resort" - Confirmed date and Source updated: Riksdagen approved the new electricity system laws 2026-06-15 (Elmarknadslag, SFS 2026:1281).
- "Energy sharing (Energidelning)" - Confirmed date and Source updated: same Riksdagen approval (SFS 2026:1281), in force 2027-01-01.
Left alone (already covered / already queued / previously rejected):
- ETS2, Central data management tool, Peppol Denmark, Changes in eSett, Requirement of electronic ID, Electricity price support, "Regret button", New terms of authentication (NO), EI accessibility of grid owner fees (no new info since the 2026-04-01 remiss already on file), Enhanced protection for district heating customers, Energy efficiency directive, RED III, WCAG, Data Hub 3.0, New REST API eSett, DK OIOUBL 3.0 - all already on the main list with no material new information found this week.
- Ei network development plan regulation update (2026-04-30) and Ei generator grid-connection remiss (2026-02-23) were found but judged to be DSO-internal reporting/technical requirements with no clear direct impact on our products' invoicing, trading, metering or customer-management functions - not queued, to keep noise down. Worth a second look if a human disagrees.
Pending Review queue total after this run: 4 items awaiting decision (all added this run; queue was empty before).
2026-08-24 - Weekly scan
Decisions processed: none. All 4 Backlog items from the 2026-08-19 run still have empty Decision cells; nothing to process.
Verification pass (18 tracked topics checked for progress since 2026-08-19): no material new decisions, dates, or guidance found for any of them - ETS2, Central data management tool, Energidelning, changes in eSett, statlig e-legitimation, elprisstöd, "ångerknapp", information regulation for grid owners, sistahandsleverantör, NO Elhub authentication/consent, gas market revenue-framework regulations, Ei grid-fee disclosure, effektavgifter/power tariffs, district heating customer protection, EU Data Hub 3.0 (DK), eSett REST API, and REMIT II. One row updated as routine maintenance:
- "Peppol Denmark" - Comment and Source updated: mandatory new Schematron validation packages (Danish CIUS 1.17.0, BIS3-Other 1.2.14) took effect 2026-08-17; documents validated only against the superseded rules may now be rejected. New source added alongside the existing one.
Flagged for closer look next cycle (no action taken, judged not yet material enough to edit a row): Norway's Elhub consent-control rollout timeline appears more advanced for residential (B2C) customers (Q1/Q2 2026) than previously understood, but no update specific to the B2B scope tracked in the "New terms of authentication and agreement (NO)" row was found - worth explicitly re-checking B2B next week.
Queued for review (Pending Review page, 2 new items):
- Awaiting your review: RME (Norway) proposal to raise electricity metering resolution for large business customers (>100,000 kWh/year) from 60 to 15 minutes, targeting 2027-01-01. Likely affects Zynergy EDM and/or AX7 metering/invoicing for NO business customers.
- Backlog: EU Hydrogen and Decarbonised Gas Market Package - Regulation applicable since 2025-02-05, national transposition deadline for the accompanying Directive passed 2026-08-05. Likely relevant to Gasell; no dedicated hydrogen-market code found in zynergy/AX7 (repos don't cover Gasell directly).
Left alone (already covered, no new information): all 4 items already in the Backlog section from the 2026-08-19 run remain undecided and were not modified. ACER Recommendation 02/2026 (network-code enforcement) and Fingrid's grid-connection-fee consultation were reviewed but judged to be non-binding/procedural at this stage - not queued.
Pending Review queue total after this run: 1 item awaiting review in "Awaiting your review", 5 items in "Backlog", 0 decisions recorded yet.