Weekly view for checkpoint status, ie executed (blue) and non-executed points (red). You can also, among other things, filtering on a checklist (head).

For checkpoints associated with checklists NOT set up with 'Generate not completed [Checkpoints]':

  • Red marking for when the item should have last been carried out (Not carried out)

  • Blue marking for each day/time the checkpoint has been carried out. Indication with a spanner/wrench if the checkpoint is marked with 'Requires action'

  • Yellow marking due today

  • Green marking for due date in the future

  • No color when the checkpoint should not have been carried out or has not been carried out

For checkpoints associated with checklist set up with 'Generate not completed [Checkpoints]':

  • Red marking for each day/time the checkpoint should have been completed

  • Blue marking for each day/time the checkpoint has been carried out. Indication with a spanner if the checkpoint is marked with 'Requires action'

  • Yellow marking due today

  • Green marking for due date in the future

  • No color when the checkpoint should not have been carried out

In this view, a summary for the number of times a checkpoint has not been performed can also be displayed (in a separate column). Appears if you enter a [From]- date as a filter. Note! Applies only to checklists set up with this functionality ‘Generate not completed [ Checkpoints]’.